U of I Trustees Could Delay Wind Turbine Decision Next Week

 

University of Illinois Trustees could postpone their decision next week on constructing a wind turbine on the Urbana campus.

Audit and Budget Committee chair Ed McMillan said it is likely the U of I will seek another extension of the grant covering $2-million of the project. Trustees will meet March 23 on the Springfield campus. Urbana Mayor Laurel Prussing addressed the committee Monday, citing citizen concerns about noise pollution and shadows. She said the U of I has failed to address those areas, and meet with the public.

"The city does support alternative energy, but these things have to be very carefully placed," Prussing said. "And this is in violation right now of the Urbana wind turbine ordinance, and we'd like to see it corrected so it would be in a good place. And we're also concerned about the total cost."

Cost for the turbine project exceed $5-million. The head of a University of Illinois Student group pushing for turbine construction says delaying the project by a few more months, after two prior extensions, won't be a large setback. Student Sustainability Committee Chair Suhail Barot predicts the turbine will remain at its current site, by the U of I's South Farms.

"I think the university's position is correct in terms of its zoning," he said. "And it terms of the overall concerns, I think issues outstanding will be resolved."

Barot said students have more doubled their financial commitment to the project through sustainability fees, and not completing the turbine soon jeopardizes losing the grant from the Illinois Clean Energy Community Foundation. He said the U of I should feel 'morally responsible' for putting up the turbine.

Prussing said the university has also failed to consider wear and tear to township roads from the project, and suggests the U of I consider investing in an existing wind farm.